Antelope High School Renovations

Project Description

Multi-phased project with multiple GMPs to allow the school to use facilities and majority of work to be completed in off school hours. Project included renovation of library, computer room, restrooms, football field lighting, sound system and construction of new science lab. Project size: 7,040 square feet.

Role of Firm/Service Provided

CM @ Risk

Lead Contractor, General Contractor, Construction Manager

Project Cost

Original: $1,536,000 – Actual: $1,416,919

Project Dates

Awarded: March 11, 2008 – Completed: February 9, 2009

Key Contact

Robert Klee 928.785.4041 – Chris Thompson 928.343.1694