EXPERIENCE AND QUALIFICATIONS

  • City of Somerton WWTP 2010: Blower and piping, odor control improvements-Contract Amount: $183,000

  • Sun Vista RV Sewer Improvements: Abandon 80 septic tanks and install 15,000 LF of main-Contract Amount: $1,111,009

  • City of Yuma Avenue D Water Main: 12” water main extension from 32nd Street to 24th Street-Contract Amount: $569,151

  • ADC 4000 Bed Expansion (McCarthy): Wet utilities including a lift station-Contract Amount: $1,832,198

  • Martinez Lake Shepard Water: Underground utilities and subdivision development-Contract Amount: $2,659,244

  • Quartzsite & Antelope Water Tanks: 500,000 gallon water tank for the Town of Quartzsite and a 120,000 gallon fire suppression water tank for Antelope  High School-Quartzsite Contract Amount: $238,323 – Antelope Contract Amount: $260,266